You are here

Mochovce

Nuclear News

Nuclear Monitor Issue: 
#767
06/09/2013
Shorts

Legal challenges against nuclear power projects in Slovakia and UK

Slovakia's nuclear watchdog violated the law when it issued a building permit for ENEL's 3.7 billion-euro nuclear reactor project, the Supreme Court has ruled. The Italian utility's local unit, Slovenske Elektrarne AS, began building two new reactors at the Mochovce nuclear power plant in 2009 after receiving a permit by the Office for Nuclear Supervision. The Supreme Court has directed the regulator to reopen the public consultation process.[1] The battle continues − the Slovak nuclear regulator UJD said it would order a new round of public consultation but that ENEL can continue with construction.

Greenpeace, along with Ireland's heritage group An Taisce (the National Trust for Ireland), have launched two independent legal challenges to the UK government plans for new nuclear power plants at Hinkley Point, Somerset. The reactor plan is being challenged on the basis of the EU's Environmental Impact Assessment Directive, which requires that affected EU members states are informed and consulted during the planning stage of infrastructure projects that "could have a significant impact on the environment". Irish people were not properly consulted on the proposals.[2]

In a separate case, Greenpeace is challenging the UK Government's decision to grant planning permission for the reactors because it hasn't found a site to store the new nuclear waste, following Cumbria's resounding rejection of a national nuclear waste site in the area.[2]

1] www.bloomberg.com/news/2013-08-21/enel-nuclear-building-permit-violated-...
[2] www.theecologist.org/News/news_analysis/2006847/legal_challenges_to_new_...

---

Greenland uranium ban may be lifted

The ban on uranium mining in the Danish realm is expected to be lifted in the Greenlandic parliament in the coming months. The first reading of the new uranium bill will be on October 1, the second on October 24 and the third in Spring 2014. The decision will then have to be confirmed in the Danish parliament. The Greenlandic government decision will be preceded by publication of two reports – one scientific and independent and one political – on the consequences of lifting the ban. The scientific report has already been written, but the government has so far refused to make it public, a fact that has caused outrage among the opposition parties.

The Greenlandic Minister of Industry and Labour has also stated that a comprehensive public debate on uranium mining is unnecessary, before the ban is lifted, because the government was given a clear mandate to do so during the recent elections.

Abolishment of the uranium zero tolerance policy is not only a hot topic in Greenland, but also in Denmark. Even though the Danish government has given notice that it favours the bill, it could still be voted down in the Parliament. The Danish government is a minority government and even within the government itself there is opposition to lifting the ban.

Avataq, the Danish Ecological Council and NOAH FoE Denmark have weighed in on the debate and last month they published a feature article in Politiken, one of the biggest Danish dailies. The article has been translated into English:
www.ecocouncil.dk/en/releases/articles-pressreleases/chemicals-and-clima...
 
− Niels Hooge

---

Uranium smuggling arrest at JFK airport. Patrick Campbell of Sierra Leone was recently caught at Kennedy Airport with uranium hidden in his shoes and luggage. He was charged with plotting to sell 1,000 tons of uranium to an FBI agent posing as a broker for Iranian buyers. He had allegedly responded to an advertisement in May 2012 on the website Alibaba.com. Campbell claimed to represent a mining company in Sierra Leone that sold diamonds, gold and uranium, and is accused of seeking to arrange the export of uranium from Sierra Leone to the Iranian port of Bandar Abbas, packed in drums and disguised as the mineral chromite.

www.nypost.com/p/news/local/nuke_powder_terror_arrest_at_jfk_MvQxJcRf5oy...
www.bbc.co.uk/news/world-us-canada-23825972

---

Plutonium and enriched uranium removed from nuclear test site in Kazakhstan. Working in top secret over a period of 17 years, Russian and US scientists collaborated to remove hundreds of pounds of plutonium and highly enriched uranium — enough to construct at least a dozen nuclear weapons — from a remote Soviet-era nuclear test site in Kazakhstan that had been overrun by impoverished metal scavengers, according to a report released in August by the Belfer Center for Science and International Affairs at Harvard. The report sheds light on a mysterious US$150 million cleanup operation paid for in large part by the US, whose nuclear scientists feared that terrorists would discover the fissile material and use it to build a dirty bomb.

www.nytimes.com/2013/08/18/world/asia/a-secret-race-for-abandoned-nuclea...

---

UK − Heysham shut down after electrical fault. Heysham 1 Power Station shut down both of its nuclear reactors after an electrical fault in a gas turbine generator. Firefighters were called to the plant on August 22. EDF Energy, which operates the plant, said it had been shut down as a precaution. In May, a reactor was shut down after smoke was seen coming from a turbine due to smouldering lagging on a turbine.

www.bbc.co.uk/news/uk-england-lancashire-23808744
http://uk.reuters.com/article/2013/08/27/uk-nuclear-idUKBRE97Q0LB20130827
www.bbc.co.uk/news/uk-england-lancashire-22394359

---

Lithuania opposes new reactor in Belarus. The Lithuanian government has made known its deep concerns about Belarus's nuclear power project near Ostroverts, and is demanding work be halted until safety issues are addressed and international treaties are complied with. Two diplomatic notes have been sent to Belarus over the past month to protest earth-moving and other initial work for the plant. "We have many concerns about safety and information we've asked for hasn't been provided," Lithuanian Prime Minister Algirdas Butkevicius said. A UN committee said in April that Belarus wasn't abiding by the terms of the Espoo Convention on cross-border environmental issues.

www.powerengineeringint.com/articles/2013/08/lithuania-express-concern-o...
ESPOO Convention: www.unece.org/env/eia/eia.html

About: 
Mochovce-3Mochovce-4Heysham-B1

Mochove: further delays and Bank Austria withdraws

Nuclear Monitor Issue: 
#745
4249
04/04/2012
Yann Louvel
Article

Bank Austria, the Austrian subsidiary of the Italian UniCredit banking group, has confirmed that by mutual agreement it will terminate a financial facility granted to Slovenske Elektrarne (SE). SE will be the operator of the Mochovce nuclear reactors 3 & 4, currently under construction.

The confirmation of the Bank Austria withdrawal came after enquiries by Global 2000 (Friends of the Earth Austria) and Greenpeace Austria."Slovenske Elektrarne has boasted in public presentations that the credit provided by private banks for its ongoing operations were in fact indirectly used to build the scrap nuclear reactors at Mochovce," said Patricia Lorenz, nuclear campaigner for Global 2000. "This is in direct contradiction with assurances made by Bank Austria earlier on the use of their credit."

In a related development Mochovce NPP operator ENEL/SE also announced early March that the two nuclear units 3 and 4 will be completed one year later than previously planned. The construction of block 3 will now be completed by the end of 2013, and unit 4 not before the middle of 2014.

"We have warned the management of Bank Austria against this risky business for months and are pleased that our negotiations have now led to some results with the bank. The completion of Mochovce 3 and 4 is again pushed a bit further away," said Niklas Schinerl, nuclear expert for Greenpeace Austria.

The reactors planned for Mochovce 3 & 4 are Soviet-type VVER 440 2nd generation reactors, which are designed without a full containment building and cannot be upgraded. As such there is a higher probability of severe accidents and the release of radioactivity.

The building of Slovakia's Mochovce 3 and 4 nuclear reactors is the longest running nuclear construction project anywhere in Europe. The reactors were designed by the Soviet Union back in the 1970s. Construction began back in 1987 but in 1992, soon after the collapse of the communist regime, it was suspended. Economic studies in 2000 showed the project to be a financial disaster.

Although operating since the mid 1980s in the Czech Republic, Slovakia and Hungary, four of the same model of reactor as Mochovce 3 and 4 under construction in East Germany, were cancelled in 1990 after the German re-unification because the reactors did not meet basic safety standards.

Russia is the only supplier of nuclear fuel for this type of reactor which makes a mockery of the idea that nuclear power provides energy security. An estimated 22 tonnes of spent nuclear fuel is generated by each reactor every year.

The investment required to build Mochovce 3 and 4 is expected to reach 2.775 billion euros. This will devour a massive 77% of SE's investment for new electricity generation 2007 to 2013. Due to the high financial risks for investors, the Slovak government provides generous state aid that is very likely illegal under EU legislation.

"The credit freeze and construction delay are new hurdles for SE and signal a victory in the fight against the building of these reactors" said Yann Louvel, climate and energy campaign coordinator for BankTrack. "As all banks financing SE know, money is fungible. They should do the same as Bank Austria and close down their credit lines with Slovenske Elektrarne to prevent the completion of Mochovce 3 and 4". BankTrack is the global network of civil society organisations targeting the operations and investments of large, international operating  commercial banks.

Source: BankTrack, Press release 15 March 2012
Contact: Yann Louvel at BankTrack,Vismarkt 15, 6511 VJ, Nijmegen, The Netherlands.
Tel: +33 (0) 688 907 868
Email: yann[at]banktrack.org
Web: www.banktrack.org

About: 
Global 2000Mochovce-3Mochovce-4

Mochovce public participation insufficient

Nuclear Monitor Issue: 
#722
6110
21/01/2011
Jan Haverkamp, Greenpeace EU energy campaigner
Article

On 14 January 2011 the Aarhus Convention Compliance Committee (ACCC) slammed Slovakia for lack of proper public consultation on the Mochovce  3,4 nuclear power project. This decision means that Slovakia also is in breach with EU law and that the European Commission will have to supervise its implementation. The decision implies that construction of the Mochovce nuclear power plant will have to be stopped until a new Environmental Impact Assessment has been carried out.

Jan Haverkamp, Greenpeace EU nuclear expert: "This groundbreaking decision shows that you cannot build dangerous nuclear power stations without taking the input of the  public into proper account. It is now up to the European Commission to keep Slovakia to its legal obligations. Mochovce construction should stop right away."

The Mochovce 3,4 nuclear power project is situated in Southern Slovakia near the Hungarian and Austrian border. It is constructed by the energy giant ENEL from Italy. It consists of two 1970s soviet design reactors that miss crucial safety features, including a secondary containment that is to protect the power station from among others attacks from outside.

Slovakia allowed active construction of the Mochovce 3,4 nuclear reactors before the public was properly consulted on the project. Greenpeace, Slovak NGO Za Matku  Zem, Global2000 (Friends of the Earth Austria) and the Viennese Ökobüro filed  complaints to Slovak courts and the UNECE Aarhus Convention Compliance Committee (ACCC) based in Geneva. The ACCC is the highest legal organ   interpreting the Aarhus Convention on access to information, public participation and access to justice in environmental matters. The ACCC decided that Slovakia was  wrong to allow construction of Mochovce without proper public participation being finished. The ACCC decision means that Slovakia will have to order a halt to  construction and re-do the public participation in the Environmental Impact  Assessment. Because the EU is a signatory to the Aarhus Convention, the European Commission is obliged to start procedures against Slovakia for breach of the  Convention and related EU directives.

Source and contact: Jan Haverkamp, Greenpeace EU campaigner dirty energy.
Tel: +32 477 790 416
Email: jan.haverkamp@diala.greenpeace.org

About: 
Mochovce-3Mochovce-4

In brief

Nuclear Monitor Issue: 
#719-720
12/11/2010
Shorts

UK & US regulators: unresolved safety issues EPR and AP1000.
On November 10, the UK nuclear regulator said it expects both the Areva EPR and the Westinghouse AP1000 reactors to have unresolved safety issues when the generic design assessment, or GDA, program completes next year. In a quarterly progress report, the NII said it has potential open issues in 10 out of 18 topical areas on the Areva EPR design review and in 16 out of the 18 topical areas on the Westinghouse AP1000 design. The GDA program was set up to issue design acceptance confirmations, or DACs, to the reactor vendors, which would see the regulator sign off on all but site specific licensing issues. The DAC could then be referenced in site license applications by utilities building the reactors. But the program has been plagued by delays resulting from NII Staff shortages and "a failure on the part of the reactor vendors to satisfy the regulator's queries", as Platts puts it.

A day earlier, World Nuclear News reported that Westinghouse has been told by the U.S. NRC that it's AP1000 aircraft impact study is not adequate. The Nuclear Regulatory Commission said that documents put to it in order to demonstrate a 2009 requirement did not include 'realistic' analyses and that this amounted to a violation of requirements that Westinghouse must explain and rectify. A rule introduced by NRC in 2009 states that  new nuclear power plant buildings and safety systems must maintain containment, cooling of the reactor core and the integrity or cooling of used fuel facilities in the event of the impact of a large passenger jet. All reactor vendors must fulfill this requirement for their designs. For Westinghouse this regulatory work comes in addition to a 2007 design amendment to the original AP1000 design, which was certified by the NRC in 2006.

In February, UK regulators already criticized the "long delays" and "poor quality" of replies they received from Westinghouse and Areva following safety reviews of their reactor designs.
Source: World Nuclear News, 9 November 2010 / Platts, 10 November 2010 / Nuclear Monitor 704, 26 February 2010


Update Belene, Bulgaria
The situation around the planned nuclear power station in Belene in Bulgaria has become unclear again. Under heavy Russian pressure (among others directly from Prime Minister Putin) and political pressure from a faction within his own party GERB around the Parliament Chair Tsetska Tsacheva, Bulgarian Prime Minister Boyko Borisov declared he is dedicated to the construction of the power plant on the shores of the Danube. Russian Atomstroyexport, a part of Rosatom, prolonged the construction contract with half a year under the condition of a price increase of maximally 2,5 billion Euro on top of the initial 4 Billion price tag. According former director of the Bulgarian Nuclear Regulatory Agency and current professor in risk analysis at the university of Vienna, Georghi Kashchiev, during a round table discussion on 18 October in Sofia, this does, however, not include the first load and large parts of the non-nuclear equipment. With that, the demand from Borisov that the total cost of the project remain under 7 billion Euro come under severe pressure. It is also unclear whether the 500 Million Euro already sunk into Belene are part of this budget. On 1 November, Bulgaria's finance minister Simeon Djankov once more confirmed that no state finances would flow into the project.

In a surprise move, Prime Minister Borisov declared on 25 October after a visit to Muenich a week earlier, that he had found a strategic investor from Bavaria for Belene. Bulgarian media speculate interest from Siemens, the engineering firm that recently broke its alliance with Areva and partnered instead with Rosatom. Siemens, however, refuses to comment on these speculations. An announcement from the Bulgarian Ministry of Economy, Energy and Tourism that the new strategic investor would be announced in the first week of November was not realised, however, and German media have remained suspiciously silent about a possible deal. On 5 November, Borisov announced an offer of up to 2% participation to each Serbia and Croatia in what he said was a pragmatic attempt to secure markets for the output of Belene.

… and Mochovce, Slovakia

Slovakia has asked and received an extension of the period of comment on the draft verdict of the Aarhus Convention Compliance Committee, that the Environmental Impact Assessment for the Mochovce 3,4 project has violated the rules of the Convention. The NGOs that originally filed the complaint, Za Matku Zem, Greenpeace Slovakia, Global2000 and the Oeko-buero Wien, did not object to an extension to 30 November. The ACCC is expected to come with a final verdict in December. A spokesperson of the Slovak nuclear regulator UJD, which was responsible for issuing construction licenses in spite of the fact that the EIA procedure had not been finalised, is currently looking for possibilities to implement a likely final verdict of the ACCC, but stated to Greenpeace that it has problems finding a proper legal pathway to do so.

An ACCC verdict is, however, binding and a breach of the Aarhus Convention is also a breach of EU legislation on Environmental Impact Assessments, which means that the European Commission would be obliged to start corrective procedures against Slovakia in case the ACCC verdict concludes a violation of the rules.

… and Temelin, Czech Republic

The submission date for the tender for five new nuclear power stations issued by the Czech utility CEZ has been extended with a year to 2013. CEZ argued that some of the contenders had asked for such an extension, though analysts are of the opinion that the lack of growth in electricity demand in the Czech Republic has bitten into the economic viability of the project. The tender for five blocks, two for Temelin and one for Dukovany in the Czech Republic, one for Jaslovske Bohunice in Slovakia and one for a still to be decided project is expected to cost around 500 billion Czech Crowns or 25 billion Euro. Each block is supposed to deliver between 1000 and 1600 MW capacity.
Source of these 3: Jan Haverkamp, Greenpeace EU Unit, email, 6 November 2010


Another fiasco at Monju, Japan.
A12-meter-long, 46-centimeter-wide, 3.3-metric-ton heavy fuel exchange component that lodged in the reactor vessel of the Monju fast-breeder reactor after being dropped on August 26, cannot be extracted using "usual methods," the Japan  Atomic Energy Agency (JAEA) has stated. The JAEA made the announcement November 9, after examining the component -a cylinder now stuck in an opening in the reactor vessel cap- with a camera. The agency believes that to get the part out, equipment on the reactor vessel cap will have to be removed, and an entirely new structure built to prevent sodium now covering the cylinder from mixing with the outside air and igniting during the process. The agency is now considering ways to do this, but gave no hint when testing of the reactor may recommence.

Since Monju resumed test operations on May 6 after shut down since a 1995 sodium leak, it has undergone the first stage of testing. These core confirmation tests were completed on July 22. Preparations were being made for the next stage, which involves increasing power output to 40%, planned for July 2011. However,  the jammed relay cylinder has made further long delays probable.
Source: Nuke Info Tokyo 138, Sept/Oct 2010 / The Mainichi Daily News, 10 November 2010


UK: What 'no subsidies' means: more help will be given.
Following lobbying by the nuclear industry the Government has accepted that it needs to give more financial incentives in order to ensure a new generation of reactors are built in the UK. Energy minister Charles Hendry said he now agreed with the industry that fixing a high minimum price for carbon emissions was not enough. Instead he thought other financial incentive measures would be need to encourage nuclear and other low-carbon energy sources.
Source: N-Base Briefing 674, 10 November 2910


IEA: US$312 billion subsidy annually for fossil.
On November 10, the International Energy Agency published its World Energy Outlook 2010. The IEA report clearly states that fossil fuels are heavily subsidized by more than US$312 billion per year globally! This leads obviously to unfair competition with clean and climate friendly renewable energies. IEA is increasingly recognizing the important role renewable energy can play to fight climate change and improve security of supply. However, it is failing to shift technology recommendations from unproven, dangerous and expensive technologies such as CCS and nuclear power plants.
Source: Press release Greenpeace, 9 November 2010

EIA Mochovce 3, 4 accepted - GP will go to court

Nuclear Monitor Issue: 
#709
6054
12/05/2010
Jan Haverkamp, Greenpeace energy campaigner
Article

On May 4, Ministry of Environment in Slovakia accepted the Environmental Impact Assessment (EIA) of the Mochovce 3 and 4 nuclear power project. Greenpeace will appeal this decision in court. The two nuclear reactors that are under construction in Mochovce in South Slovakia are of the 1970s VVER 440/213 design and received a building permit in 1986. Among others, this outdated design misses a so called secondary containment and therefore crucial protection against leakage of nuclear material after a large accident as well as against malevolent attack from outside.

Originally, the Slovak government and Mochovce operator Slovenske Elektrarne, which is 67% owned by the Italian electricity giant ENEL, did not want to do an EIA at all. In 2008 they conceded to pressure from environmental organisations, the neighbouring countries Hungary and Austria as well as the European Commission. An EIA is to build the basis for the environmental justification of the project - it has to assess which impacts the project will have on the environment and whether these impacts can be justified in comparison with alternatives.

The Aarhus Convention, which delivers the legal basis for Environmental Impact Assessments, stipulates that public participation processes like the EIA have to be carried out when all options are still open. Only in that way, conclusions from the EIA procedure can be reflected in the project and only in that way information and opinions on the project can be assessed without pressure of possible loss of investments. Still, SE / ENEL started construction of Mochovce 3,4 in November 2008 in spite of the EIA procedure only just having started. With this, the EIA procedure is in breach with the Slovak law on EIA, the EU Directive on EIAs and the Aarhus Convention.

The EIA report furthermore lacks crucial information to enable the above mentioned justification. SE / ENEL refused to include alternatives, the environmental impacts of fuel production and radioactive wastes, as well as infrastructure projects involved in securing cooling water. Beyond design accidents were not analysed and a part from Hungary that lies within the 30 km emergency zone was conveniently excluded as well.

Greenpeace will appeal the decision of the Ministry of Environment in court. There is already a complaint against the EIA procedure running for the Aarhus Compliance Committee in Geneva, which is expected to come with a verdict before summer. Also the European Commission is investigating the process.

Greenpeace is furthermore already in court because of a conflict of interest of the auditor of the final EIA report. The Ministry of Environment had hired the DECOM consultancy for that task, which is 100% owned by the main construction contractor for Mochovce, VUJE.

The Slovak Parliament changed recently the law on access to information as well as the nuclear law, preventing the public access to any nuclear information - again in breach with EU Directives and the Aarhus Convention.

Jana Burdova, spokes person of Mochovce, said today that "this is the last step in the EIA process". Unlikely so. The court case will take several  months at least. In Bulgaria, a comparible court case took more than four years.

Source and contact: Jan Haverkamp, Greenpeace energy campaigner expert on energy issues in Central Europe.
Tel: +32 2 27419 21
Email: jan.haverkamp@diala.greenpeace.org

 

About: 
Mochovce-3Mochovce-4

Slovakia - the ghost of Soviet nuclear - continued

Nuclear Monitor Issue: 
#706
6032
26/03/2010
Jan Haverkamp
Article

In 2007, the European Greens developed a video to illustrate the atmosphere of manipulation around the development of the Mochovce 3 and 4 nuclear power blocks in Slovakia. It had the title “the Ghost of Soviet Nuclear”. Then, it referred to the fact that an Environmental Impact Assessment (EIA) for this 1970s designed nuclear reactor was refused on the basis of a valid 1986 construction permit – issued well before the ousting of the communist regime in 1989. Also, finances were tweaked by capping the fees for decommissioning and waste for Slovenske Elektrarne (SE), the 66% daughter of the Italian utility ENEL, and financial advantages including a no-dividend period for 34% owner the Slovak State.

Since the release of "the Ghost of Soviet Nuclear" video in 2007, under pressure from the public, a court case run by over a hundred complainants initiated by Greenpeace and Za Matku Zem, and complaints from the European Commission, ENEL and the Slovak Government gave in and started an EIA procedure in 2009. The public was invited to submit comments and hearings were organised in Bratislava, Vienna and Ezstergom (Hungary). ENEL wanted to show that it had nothing to fear and that it can play to the rules. Well, not exactly. From the start, ENEL made clear it did not want to wait for the outcome of the EIA procedure before starting construction. ENEL Director Paolo Ruzzini was shocked by the delay that 4,5 years of court procedures had caused to the Belene nuclear project in Bulgaria and it was made clear from the start that the EIA was not going to cause any delays. The Slovak government allowed the EIA to be finished only before the final operation licence would be given – construction could start.

In the run-up to the EIA hearings, Mochovce spokes person Robert Holy produced a power point presentation to discuss with the Ministry of Environment how to reduce the impact of these meetings. Unfortunately, this document landed in the hands of Energia Klub and Greenpeace in Hungary. The proposed prevention of a hearing in Vienna or blocking dissent by organising a demonstration from nuclear workers in front of the hearing venue did not work. Although the presentation prominently stated that public and media attention had to be kept to the minimum, partly because of this gaffe, the hearings got wide international media coverage. The town of Vienna collected over 200.000 submissions to the EIA procedure. Also Hungary was active, not in the least because of the fact that Hungarian territory in the 30 km zone around Mochovce was conveniently left out of the analysis and emergency organisation structure.

ENEL / SE finished their responses on the input from the public in the end of 2009. From the 99 submissions made by Greenpeace International, 90% was not addressed or the response diverted from the issues raised. Only 3 suggestions were taken over, 2 of them concerning the quality of English of the text. Alternatives were not deemed necessary, the reservoir near the town of Slatina that was build – according to its own EIA – to guarantee cooling water for Mochovce had according to SE nothing to do with the project, nuclear safety and security were not issues to be discussed in an environmental impact assessment. Of course, such omissions and blatant disregard for public participation will be corrected by the responsible authority – in this case the Slovak Environmental Ministry. The Ministry gave an independent auditor the task of assessing all input in the EIA. Independent? Well, not exactly. The auditor is director of the DECOM consultancy, a 100% daughter of VUJE, the main construction contractor of Mochovce 3 and 4. The final assessment therefore follows virtually completely the promoter's remarks. The Ministry finds itself now in court after Greenpeace appealed against this situation.

In the mean time, ENEL / SE started construction. Prime Minister Robert Fico already had cut the ribbon on 3 November 2008, but that was merely a symbolic act to give some pro-nuclear input to the European Nuclear Energy Forum that was to start the next day in Bratislava. The Aarhus Convention on public participation, however, prescribes that public participation, like that during an EIA, has to take place when all options are still open. In plain language that means, before construction is started. The independent building authority UJD, which also happens to be the nuclear regulator, had to give several permissions to continue on the basis of the myriad of changes made in the project. It could have easily held those until the EIA procedures would be finalised, but the Slovak government and ENEL pressed on and UJD gave the go-ahead. As a result, the entire EIA procedure is now under investigation by the UNECE Aarhus Compliance Committee, which is expected to give a verdict before summer. And when the Ministry comes with its final verdict on the EIA report, it is likely that Greenpeace and Za Matku Zem will go to court to test these irregularities also under Slovak and European law.

International Day of Action
Because of the EIA manipulations, concern in Austria has also been growing. A coalition of NGOs has called for a day of action on 24 April, just before Chernobyl Day, to highlight the link between the Soviet Ghosts of that catastrophe and Mochovce, which is only 150 km away from Vienna.

ENEL also ran into trouble with financing the estimated 3 billion Euro budget. In 2008, a bank-loan of 800 million Euro was frozen on request of the nine bank strong consortium because of concerns about the Mochovce project. ENEL then decided to fund the project from its own reserves and now taps into the proceeds of billions of Euros received by the issuing of bonds. Needless to say, none of the bond prospectuses mentions the risks attached to Mochovce.

The Soviet Ghost does not only appear around Mochovce. Slovakia started procedures for a sixth block at the nuclear power plant in Jaslovske Bohunice. This is to be developed by the state utility JAVYS, that is also responsible for nuclear waste and the decommissioning of the three closed blocks in Bohunice. Slovakia chose as strategic partner the Czech energy giant CEZ, of which JAVYS and SE used to be a part before Czecho-Slovakia split in 1993. The choice was made without a public tender, although according to Economy Minister Jahnatek 17 firms had expressed interest. But friends come first. This, however, is against European procurement rules and the European Commission is currently investigating whether the choice of CEZ is not illegal. In the mean time, JAVYS and CEZ founded the firm JESS for implementation of the plan for a new nuclear reactor. CEZ is currently tendering for a constructor of five nuclear power stations in the hope to get a mass-discount. One or maybe even two of them would be destined for Bohunice. Speculation runs wild about whether this will go to the Russian / Czech consortium lead by Skoda JS or whether the former-Soviet friends will dare to open up to something new.

Source: Jan Haverkamp, Greenpeace EU Energy Campaigner, Email: jan.haverkamp@greenpeace.org
Contact: * about the International Day of Action against Mochovce: Atomkraftfreie Zukunft, Paula Stegmüller - atomkraftfreiezukunft@gmx.at / * about the Aarhus complaint: Global2000, Patricia Lorenz – patricia.lorenz@foeeurope.org / * about the EIA in Slovakia: Greenpeace, Andrea Zlatnanska – andrea.zlatnanska@greenpeace.sk / * about the investigations of the European Commission: Greenpeace Jan Haverkamp – jan.haverkamp@greenpeace.org

About: 
Mochovce-3Mochovce-4